How to Confirm Interior Door Handing Before Ordering
Confirm interior door handing with a plan-view drawing that identifies the viewing side, hinge side and direction of swing. Add the supplier's agreed handing code only after those physical details are clear. A message saying "right hand" is not a complete machining instruction.
Handing errors can affect the hinge jamb, strike preparation, door edge, lock function and hardware orientation. An unmachined symmetrical slab may offer flexibility, but a prepared door set should never be assumed reversible without checking every component.
Why two people can describe the same door differently
One person may describe the opening from the corridor, while another stands inside the room. A hardware supplier may also use a convention that differs from the carpentry convention used to order the door. Schlage specifically distinguishes lever handing from the way doors are described for carpentry.
Avoid resolving this by choosing whichever abbreviation appears most familiar. Establish a shared reference that the purchaser, manufacturer and installer can all reproduce.
Record the door in plain language first
For each opening, identify the room names on both sides. Then write a physical description such as: "Viewed from corridor toward bedroom, hinges are on the left, and the leaf swings away from the observer into the bedroom." This description remains understandable even before an LH or RH code is assigned.
Include a plan view showing the hinge pivot and the arc of the open leaf. Mark the observation arrow and distinguish the closed leaf line from the open position. If the project uses a secure side, identify that separately; "outside" can be ambiguous for two internal rooms.
Confirm what handing changes in the supplied set
| Component | Point to check |
| Leaf | Hinge edge, latch edge, bevel and any unequal faces |
| Frame | Hinge jamb, strike jamb and position of stops or rebates |
| Lock or lever | Function, secure side and model-specific reversibility |
| Hinges | Orientation and handing requirements for the selected model |
| Double door pair | Active leaf, inactive leaf and closing sequence |
Some levers can be reversed during assembly. That does not make the entire door and frame reversible. A frame already machined for a strike on one side may still need a different preparation.
Approve a first opening before releasing the batch
Choose one representative door mark and place its plan, elevation, hardware model and machining detail on the same approval record. Check the view from both rooms. Confirm the room-side privacy control or key function where applicable, and make sure the open leaf does not conflict with the intended room layout.
For an order with repeated openings, group quantities by the approved handing diagram. Keep left and right versions under separate item codes rather than mixing them under one size description. Carry those codes onto the packing list and product labels.
If a later drawing revision changes the swing, identify every affected component. Changing an arrow in a schedule is not sufficient if production has already received an earlier machining drawing.
A practical handing approval record
- Door mark and names of both adjacent spaces.
- Observation arrow and hinge location.
- Swing arc and agreed handing code.
- Lock function and hardware reference.
- Active leaf and closing order for a pair.
- Approved drawing revision and quantity.
Common buyer questions
Is a photo enough to confirm handing?
A photo can help, but it may not show both sides, the viewing direction or the intended swing. Combine it with a labeled plan view.
Can a right hand door become a left hand door on site?
Only if its construction, frame and hardware preparations permit the change. Confirm this before ordering rather than relying on site modification.
What should a distributor send the factory?
Send a door schedule with quantities tied to approved swing diagrams. Include the hardware models and any room-side function requirements.
For prehung or machined interior doors, send Shinystar Wood the marked plans and hardware information so the handing can be reviewed together with the preparation scope.